(SIZE 550M x 3.25 M)
3.25 m Width Horse Shoe Section Irrigation Department Tunnel Executed near Karjat (Ahemadnagar Dist) by Introducing Chain Mounted BOBCAT Excavator for loading of Blasted Stuff.
320 Level Chikhala Opencast Mines Development of MOIL, by means of Mechanical means at Chikhala, Dist- Bhandara.
Drilling at Mithi River, Mahim, Mumbai for underwater Blasting, for widening and deepning of Mithi River, Project of MMRDA,Mumbai.
Rock Cutting by Noiseless Blasting by using method of Diamond Core cutting in Bangalore City.
(MUMBAI-AGRA FOUR LANING)
Controlled Blasting work conducted at NHAI-3 near Ghoti Hill, Igatpuri, work allotted to Sadbhav Engineering Limited.
Cautious controlled Blasting for proposed DLI Hydro Power Project,Darana Dam, Nashik,Maharashtra.
Blast Induced Vibrations Monitoring by VMS 2000, Thomas Vibrograph, at Darana Dam, Nashik, Maharashtra.
Development work by mechanical means at Hiwara Manganese Mines, Bhandara,Maharshtra.
Underwater Blasting conducted at Mithi River, Mahim,Mumbai.
Controlled Blasting in Trenching for laying of Storm Water Pipeline at Godavari River Bed, Nasik; work of Nasik Municipal Corporation, Nashik.
Deep Hole Controlled Blasting at Paradgaon Stone Quarry (DGMS approved Mine) at Paradgaon, Nagpur.
Charge Preparation for Pre- Split Blasting for profile cutting at Avantha Power Plant, Barella, Seoni, Madhya Pradesh.
Controlled Blasting work near Structure at Tarwala Nagar near Nasik.
Laying of Blasting Pads for Muffling to arrest any Fly Objects near sensitive structure at Tarwala Nagar,Nasik.
Large Dia controlled blasting using bottom hole spacers to reduce ground vibrations at Avantha Power Plant, Seoni,Madhya Pradesh.
Dy.Director of Mines Safety Mr. Rafique with our Mining Statutory staff at Boregaon(J) Quarry, Saoner, Nagpur during his visit to Mine.
Advice on Fixation of safe charge under guidance of CMRI, Nagpur Region at Boregaon(J) Quarry, Saoner, Nagpur.
CMRI Principal Scientist Dr.Ramulu visit to Power Plant regarding institute advice on controlled blasting to minimize vibrations at Unit # 8.
Controlled Blasting work at Wagon Tippler, adjacent to Railway Track, Unit # 7, Power Plant, Maharashtra.
Blast executed in ore body with development of mines by mechanical.